Construction project designation:
Ferlach municipality, wastewater treatment plant, BA07 – ARA Ferlach
Execution period:
Nov. 2009 – Dec. 2011
Project description:
The subject of the project was the adaptation to the state of the art technology of the existing wastewater treatment plant with the capacity of 10,000 residents. The treatment plant is used for cleaning the wastewater from the Ferlach municipality area. The cleaning capacity of the entire plant was adapted to the state of the art technology. After the complete biological treatment in the wastewater treatment plant, the wastewater is discharged into the Drau river.
Project cost:
€ 3,700,000.00